Fahi Dhiriulhun Corporation Limited · Government of Maldives
|
All projects
OngoingUpdated 2026-04-22

AMAN Udhares / AMAN Dhoadhi

އަމާން އުދަރެސް / އަމާން ދޮޑި
Hulhumalé Phase 2 · Kaafu Atoll

Overview

A 2,000-unit social housing development financed under a government-to-government credit line. EPC signed 8 March 2021; works commenced 8 December 2021 with a 1,125-day contract duration.

Key numbers

Total units
2,000
Progress
62%
Contract value
USD 137 million
Duration
1,125 days

Unit breakdown

TypeSizeCount
Three-bedroom apartments900 sqft1,400
Two-bedroom apartments650 sqft600

Timeline

  1. Commencement
    2021-12-08
  2. Latest update
    2026-04-22
  3. Target completion
    TBA